Decision details
The East Sussex (B2123 The Drove, Falmer)(Temporary Layby Closure) Order 2021
Decision Maker: Director of Communities, Economy and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To allow East Sussex County Council and
Brighton and Hove City Council to store equipment for the
bridleway/ cycleway improvement works, East Sussex County Council
have made an Order under Sections 14(1) and 15(1)(b) of the Road
Traffic Regulation Act 1984, as amended, which will temporarily
close the following length of layby;
Decision:
A safe route will be provided for pedestrians
and vehicular access for residents and to properties maintained
whenever possible.
The Order commences on 26 April 2021 and lasts for a period of 18
months, or until works are completed, whichever is earlier.
However, it is anticipated works will be undertaken between 26
April & 23 July 2021 depending upon the weather
conditions.
If you require further information telephone Network Management on
0345 60 80 193.
Alternative options considered:
Temporary Layby Closure
The Drove (eastern side) – approximately 1210 metres south of
the junction with U5048 Park Street, south-eastwards for a distance
of 47 metres.
Publication date: 16/04/2021
Date of decision: 23/04/2021