Decision Maker: Director of Communities, Economy and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To allow Network Rail to carry out maintenance
works, East Sussex County Council have made an Order under Sections
14(1) and 15(1)(b) of the Road Traffic Regulation Act 1984, as
amended, which will temporarily close the following length of
road;
Temporary Road Closure
Station Approach - 20 metres either side of the level
crossing.
A safe route will be provided for pedestrians and vehicular access
for residents and to properties maintained whenever possible with
an alternative route for through traffic westbound via A259 New
Road – A259 Flyover Slip on eastbound – The Drove
– B&Q roundabout – The Drove - South Way - Lewes
Road - North Way – The Drove – North Quay and eastbound
via A259 Drove Road – The Drove – South Way –
Lewes Road – North Way – The Drove – Flyover slip
off – A26 New Road.
The Order commences 22 November 2021 and lasts for a period of 18
months, or until works are completed, whichever is earlier.
However, it is anticipated works will be undertaken from 23:30hrs
on 22 November to 04:30hrs on 23 November 2021 depending upon the
weather conditions.
If you require further information telephone Network Management on
0345 60 80 193.
Publication date: 12/11/2021
Date of decision: 19/11/2021