The East Sussex (A259 Pevensey Bay Road, Eastbourne / A259 Eastbourne Road, PevenseyBay) (Temporary Prohibition of Traffic) Order 2018

Decision Maker: Director of Communities, Economy and Transport

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To allow East Sussex Highways to carry out carriageway resurfacing, East Sussex County Council have made an Order under Sections 14(1) and 15(1)(b) of the Road Traffic Regulation Act 1984, as amended, which will temporarily close the following lengths of road in phases;


Decision:

A safe route will be provided for pedestrians and vehicular access for residents and to properties maintained whenever possible with an alternative route for through traffic signed and maintained for the duration of the works via A259 Eastbourne Road, Pevensey – A259 Wallsend Road, Pevensey – A27 Pevensey Haven Roundabout, Pevensey – A27 Pevensey Bypass, Westham – A22 Golden Jubilee Way, Westham – A22 Shinewater Roundabout, Langney – A2290 Lottbridge Roundabout, Hampden Park – A2290 Lottbridge Drove, Eastbourne – A259 Seaside Roundabout, Eastbourne – A259 Seaside, Eastbourne – A259 Langney Roundabout and vice versa.

The Order commences 23 August 2018 and lasts for a period of 18 months, or until the works are completed, whichever is the earlier. However, it is anticipated the works will be undertaken as detailed above, depending upon the weather conditions.

If you require further information telephone Network Management on 0345 60 80 193.

Alternative options considered:

Temporary Road Closures – from 20:00 hours and 06:00 hours
Phase 1 - A259 Pevensey Bay Road/A259 Eastbourne Road - from the junction of U2379 Pacific Drive, Eastbourne to the junction of U7281 Grenville Road, Pevensey Bay, a distance of 1,500 metres. The works are due to be carried out between 23 and 25 August 2018.

Phase 2 - A259 Pevensey Bay Road - from the junction of the A259 Crumbles roundabout to the junction of the A259 Langney roundabout, a distance of 800 metres. The works are due to be carried out between 28 August and 7 September 2018

Publication date: 10/08/2018

Date of decision: 10/08/2018