Issue - decisions

HS/3258/CC

16/10/2015 - The construction of a Primary play space area (12m x 7m) together with 3 storage units (2m x 0.9m) and a timber garden room (approximately 8.1m x 4.5m and 2.5m in height) to the south east of the School site. To be provided between the hours of 7.30

20.1     The Committee considered a report by the Director of Communities, Economy and Transport.  The Chair reported that the Local Member supported the proposal. 

 

20.2     Members have considered the officer’s report and agree with the conclusion and reasons for recommendation as set out in paragraph 7 of the report.

 

20.3     RESOLVED to grant planning permission subject to the following conditions:

 

1.      The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.

        

         Reason: To comply with Section 91 of the Town and Country Planning Act 1990.

 

2.      The development hereby permitted shall be carried out in accordance with the plans listed in the Schedule of Approved Plans.

        

         Reason: For the avoidance of doubt and in the interests of proper planning.

 

3.      No construction may take place until the detailed specification of the absorptive acoustic barrier (as recommended in the MRL Acoustics Report, dated February 2015) has been submitted to and approved in writing by the Director of Communities, Economy and Transport.  The MUGA hereby approved shall not be brought into use until the acoustic barrier has been installed in accordance with the approved specification.

        

         Reason: To protect the amenity of nearby residential properties in accordance with Saved Policy DG1 of the Hastings Local Plan 2004.

 

4.      The use hereby permitted shall not be carried out other than between the hours of 07.30 - 19.30 on Monday to Friday inclusive and the hours of 10.00 - 17.00 on Saturdays and Sundays with no use taking place on Public and Bank Holidays except for works of essential maintenance or to respond to an emergency,  and after the carrying out of such works full details of the time, date, reason for and nature of the works shall be given in writing to the Director of Communities, Economy and Transport.

        

         Reason: To safeguard the amenities of the occupiers of properties in the vicinity of the site and to comply with Saved Policy DG1 of the Hastings Local Plan 2004.

        

5.      The development hereby permitted shall be carried out in accordance with the Traffic Management Scheme, submitted 2nd June 2015.

        

         Reason: In the interests of highway safety and for the benefit and convenience of the public at large in accordance with Saved Policy TR2 of the Hastings Local Plan 2004.

        

6.      No construction works shall take place in connection with the development hereby approved at any time, other than between the hours of 08.00 and 18.00 hours on Mondays to Fridays, and not at any time on Saturdays, Sundays, Bank and Public Holidays unless the prior written agreement has been received from the Director of Communities, Economy and Transport.  Deliveries will be within the times specified in the Transport Management Scheme.

        

         Reason:  In the interest of the amenities of the locality in general and adjoining residential properties in particular and to accord with Saved Policy DG1 of the Hastings Local Plan 2004.

 

Schedule of Approved Plans

 

Waste Management Plan, Noise Impact Assessment, 6222/D/0022 - Site Location Plan, PS 3 - Combination Component Details, PS 5 - Storage Unit Component Details, Supplementary Form, Design and Access Statement 22.04.15, 6222/D/7033 - Proposed Site Plan including Acoustic Fencing, Traffic Management Scheme, Dimensions for the garden room.