Decision Maker: Lead Member for Transport and Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
The County Council’s Transport Development Control team is looking to introduce an amended mechanism for how developer led highway works are agreed with the County Council. Currently this is generally through Section 278 agreements, which will remain the case for the majority of schemes. However, where the proposed highway works are of a low value and present minimal risk to the County Council’s highway asset, a new light touch process is proposed to be introduced. This will be in the form of Mini Section 278 agreements. The report to Lead Member will seek approval for this approach, along with the proposed guidance on this matter to be published.
64.1 The Lead Member considered a report by the Director of Communities, Economy and Transport.
DECISIONS
64.2 The Lead Member RESOLVED to approve the use of the “Minor Works Agreements under Section 278 legal agreement process for development related highway works.
REASONS
64.3 The use of Minor Works S278 Highway Works Agreements and associated Developer Guidance Notes will provide an improved service to customers and will most efficiently and effectively manage development related highway works.
Report author: Michelle Edser
Publication date: 11/03/2024
Date of decision: 11/03/2024
Decided at meeting: 11/03/2024 - Lead Member for Transport and Environment
Effective from: 16/03/2024
Accompanying Documents: