Decision Maker: Director of Communities, Economy and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To allow SGN to install a new gas service,
East Sussex County Council have made an Order under Sections 14(1)
and 15(1)(b) of the Road Traffic Regulation Act 1984, as amended,
which will temporarily close the following length of
road;
A safe route will be provided for pedestrians
and vehicular access for residents and to properties maintained
whenever possible with an alternative route for through traffic via
A268 Cinque Ports Street/Tower Street/Fishmarket Road - A259
Fishmarket Road/South Undercliff/Strand Quay - A268 Wish
Street.
The Order commences 19 October 2020 and lasts for a period of 18
months, or until works are completed, whichever is earlier.
However, it is anticipated works will be undertaken between 19
& 23 October 2020 depending upon the weather conditions.
If you require further information telephone Network Management on
0345 60 80 193.
Temporary Road Closure
Cinque Ports Street - from its junction with A268 Station Approach
to its junction with A268 Ferry Road
Publication date: 09/10/2020
Date of decision: 16/10/2020