Decision details

Eastbourne Town Centre Improvement Scheme Phase 2a (Terminus Road: Bankers Corner to Langney Road)

Decision Maker: Lead Member for Transport and Environment

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To consider the final design of the Eastbourne Town Centre Improvement Scheme Phase 2a ahead of advertisement of the associated Traffic Regulation Orders and construction

Decisions:

11.1     The Lead Member considered a report by the Director of Communities, Economy and Transport, together with a petition which had been submitted to the County Council.

 

11.2     Mr Andy Spirou spoke on behalf of the petitioners, to request an extension to the road closure in Bolton Road to assist with al fresco dining.

 

11.3     Officers confirmed that, based on available budget and without having to revisit design work, a small amendment to the scheme by extending the closure approximately 10m to the south could be accommodated without the need for further consultation or impacts on funding.  Officers further confirmed that Eastbourne Borough Council had agreed to the designation of five disabled parking bays in Hyde Gardens, which would lead to a net gain of three such spaces. 

 

DECISIONS

11.4     The Lead Member RESOLVED to (1) approve the final detailed design for the Eastbourne Town Centre Improvement Scheme as set out in Appendix 2 and in paragraph 11.3;

 

(2) approve the construction of the scheme in accordance with the final detailed design;

 

(3) delegate authority to the Director of Communities, Economy and Transport, in consultation with the Lead Member, to make any necessary minor amendments to the scheme; and

 

(4) approve publication of the associated Traffic Regulation Orders.

 

Reasons

 

11.5     Phase 2a of the Eastbourne Town Centre Movement and Access Package focuses on the section of Terminus Road between Bankers Corner and Langney Road and builds on the earlier phase that was completed in January 2020.  The shaping of the final detailed design has been positively influenced in a number of ways through the ongoing engagement with Eastbourne town centre stakeholders, the outcomes of the access assessment undertaken on the scheme design and the Equalities Impact Assessment (EqIA).  This has resulted in changes to the palette and location of materials and street furniture being used within the scheme design to address any impact on groups with protected characteristics. 

 

11.6     In addition, alternative provision of on road blue badge parking in the town centre, as well as in surface car parks, has been sought to negate the loss in current blue badge spaces in Bolton Road and Langney Road area.  Officers will continue to investigate alternate provision.  The necessary Traffic Regulation Orders related to the Pedestrian Zone in Terminus Road as well as changes to traffic movements and parking restrictions required as part of the scheme will be advertised later in the summer.

 

Report author: Rupert Clubb

Publication date: 21/07/2021

Date of decision: 19/07/2021

Decided at meeting: 19/07/2021 - Lead Member for Transport and Environment

Effective from: 28/07/2021