Decision Maker: Chief Operating Officer
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
This is for pre contract services to enable a
tender to be prepared for a new 2000sqm building providing PMLD
pupil places for Secondary and Sixth Form pupils on the Grove Park
Primary School site. The existing primary school will have minor
alterations and a new nursery provision will be provided on the
same site. Two mobile classrooms will be removed.
Capital funding has been allocated in the Capital Programme to
accommodate the new facilities at Grove Park School. The site will
therefore have a nursery, primary school and new secondary/sixth
form accommodation. The pupils will be between the ages of 2 to 18
years.
The Pre-Contract Services Agreement (PSCA)
contract for feasibility studies in relation to a new Profound and
Multiple Learning Disability (PLMD) building for Grove Park
Secondary and Sixth Form on a Council owned site in Crowborough has
been award to Willmott Dixon.
Various possible procurement routes to market
were considered and the most suitable was selected.
Publication date: 28/06/2023
Date of decision: 26/06/2023
Effective from: 05/07/2023