Decision details

The East Sussex (A259 Wallsend Road, Pevensey)(Temporary Prohibition of Traffic) Order 2023

Decision Maker: Director of Communities, Economy and Transport

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To allow Network Rail to carry out works, East Sussex County Council have made an Order under Sections 14(1) and 15(1)(b) of the Road Traffic Regulation Act 1984, as amended, which will temporarily close the following length of road;

Decision:

Temporary Road Closure
Wallsend Road – 10 metres either side of the level crossing

A safe route will be provided for pedestrians and vehicular access for residents and to properties maintained whenever possible with an alternative route for light vehicles via A259 Wallsend Road – A259 Eastbourne Road – A259 Pevensey Bay Road – A259 Martello Roundabout – A259 Pevensey Bay Road – A259 Crumbles Roundabout – A259 Pevensey Bay Road – A259 Langney Roundabout – B2104 Langney Rise – B2104 Hide Hollow Roundabout – B2191 Hide Hollow – B2191 Priory Roundabout – B2191 Hide Hollow – B2191 Eastbourne Road – B2191 High Street – B2191 Castle Road – B2191 High Street – A259 Wallsend Road and vice versa.
HGVs via A259 Wallsend Road – A259 Eastbourne Road – A259 Pevensey Bay Road – A259 Martello Roundabout – A259 Pevensey Bay Road – A259 Crumbles Roundabout – A259 Pevensey Bay Road – A259 Langney Roundabout – A259 St Anthonys Avenue – A259 Seaside Roundabout – A2290 Lottbridge Drove – A2290 Birch Roundabout – A2290 Lottbridge Drove – A2290 Lottbridge Roundabout – A22 Highfield Link – U2221 Willingdon Drove – A22 Golden Jubilee Way – A22 Dittons Road Roundabout South – A22 Golden Jubilee Way - A27(T) Dittons Road Roundabout North – A27(T) Pevensey Bypass – A27(T) Pevensey Haven Roundabout – A259 Bexhill Road – A259 Wallsend Road and vice versa.

The Order commences 7 August 2023 and lasts for a period of 18 months, or until works are completed, whichever is earlier. However, it is anticipated works will be undertaken as detailed below, depending upon the weather conditions.

Between 7 & 11 August 2023
From 22:00hrs to 05:00hrs between 1 & 3 November 2023

If you require further information telephone Network Management on 0345 60 80 193.

Publication date: 28/07/2023

Date of decision: 04/08/2023