Award of contract to carry out the final business case development for the A22 Major Road Network corridor scheme

Decision Maker: Director of Communities, Economy and Transport

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Jacobs UK Ltd (Jacobs) were commissioned through a direct award via the ESPO Consultancy Framework in September 2024 to undertake the production and submission of the A22 MRN Corridor FBC. Jacobs were appointed due to their previous knowledge and experience in supporting the County Council in delivering the outline business case submitted to the Department for Transport in December 2022 and which was approved in May 2024.

The original contract value was estimated at £469,000 based on time and materials. Additional hours have been subsequently identified to undertake the following 5 elements related to the full business case and wider A22 project activities:
• Consultation programme
• Programme extension/co-ordination with detailed design
• A22 Scheme Development - Client Support
• Active travel measures - Western Road option development
• Support EIA screening (cumulative impacts & biodiversity assessment

The proposal for the additional hours exceeds the original contract estimate by a further £362,000. Although allowable under the contract with Jacobs, the new estimated total value of £831,000 triggers a Key Decision as it will result in the Council incurring expenditure which is above £500,000 per annum.

The modification of the existing contract was signed off by the Head of Procurement and the Director for Communities, Economy and Transport on 20 March 2025.

Decision:

Increase in value to previously let contract with Jacobs for A22 Major Road Network (MRN) Corridor Full Business Case (FBC).

Alternative options considered:

The option to not award the contract value increase and therefore remain at original contract value was considered. This would mean that the Full Business Case (FBC) and wider A22 project activities could not be fully completed. Not being able to submit the FBC to the Department for Transport for approval could result in the potential cessation of the project and delivery of the MRN scheme.

Publication date: 20/03/2025

Date of decision: 20/03/2025