Decision details

Eastbourne Town Centre Phase 2B Experimental Traffic Regulation Orders

Decision Maker: Lead Member for Transport and Environment

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Further to the Lead Member approval for Eastbourne Town Centre Movement and Access Package Phase 2b & Victoria Place Levelling Up Fund (Seaside Road to Grand Parade) to progress to detailed design and construction, a further decision is required on the proposal to implement an experimental Traffic Regulation Order on Phase 2b. This would allow for options regarding timings of restricted hours to be explored for each phase to identify the most suitable hours for the local traders and/or residents.

Decisions:

37.1     The Lead Member considered a report by the Director of Communities, Economy and Transport.

 

DECISIONS

 

37.2     The Lead Member RESOLVED to:

 

(1) note the previous development work that has been undertaken in relation to the Eastbourne Town Centre Movement and Access Package 2b, ‘Victoria Place’ project; and

 

(2) agree that Experimental Traffic Regulation Orders are advertised post construction in relation to vehicular access and timings within the Eastbourne Town Centre Movement and Access Package Phase 2b ‘Victoria Place’ project.

 

REASONS

 

37.3     The Eastbourne Town Centre Movement and Access Package: Phase 2b and ‘Victoria Place’ scheme, has received substantial Levelling Up Fund investment via Eastbourne Borough Council, to enhance pedestrian safety and accessibility in Eastbourne’s town centre. The County Council is acting as the project deliverer for the scheme, which must be delivered by March 2026.

 

37.4     Experimental Traffic Regulation Order (ETRO) will be advertised on completion of construction in relation to vehicular access and timings on the scheme based on continued stakeholder engagement and feedback received and to ensure the County Council meets its statutory duties for consultation on Traffic Regulation Orders.

 

37.5     Following the outcomes of the ETRO a further report detailing any objections made, will be presented to the County Council’s Planning Committee for its consideration.

Report author: Ellie McDaniel

Publication date: 08/12/2025

Date of decision: 08/12/2025

Decided at meeting: 08/12/2025 - Lead Member for Transport and Environment

Effective from: 16/12/2025

Current call-in Count: 0