Decision details

Proposed improvements at the Sackville Road Roundabout, Bexhill

Decision Maker: Lead Member for Transport and Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

To consider the outcome of the review of the detailed design work and agree which roundabout layout should be taken forward for construction as part of the 2016/17 capital programme for local transport improvements

Decisions:

60.1     The Lead Member considered a report by the Director of Communities, Economy and Transport.  The written comments of Councillor Ensor were noted. 

 

DECISIONS

 

60.2     RESOLVED to (1) note the outcomes of the review of the detailed design work associated with the proposed improvements at the Sackville Road Roundabout, Bexhill;

 

(2) agree that the alternative design (Figure 2 of Appendix 1) should be taken forward to detailed design and construction as part of the 2016/17 capital programme for Local Transport Improvements; and

 

(3) agree that the draft Traffic Regulation Order to enable changes to be made to the on-street parking arrangements on Marina to facilitate access to the west end stage door of the De La Warr Pavilion be made.               

 

Reasons

 

60.3     As part of the ongoing value engineering exercise, an alternative design has been developed, which significantly reduces the overall cost and impact during construction whilst retaining the main aims and benefits of the original scheme.                                     

 

Report author: Rupert Clubb

Publication date: 21/03/2016

Date of decision: 14/03/2016

Decided at meeting: 14/03/2016 - Lead Member for Transport and Environment

Effective from: 22/03/2016