Golden Jubilee Way - from the junction with
A22 Shinewater roundabout to the junction with A22 Dittons Road
roundabout South.
A safe route will be provided for pedestrians and vehicular access
for residents and to properties maintained whenever possible with
an alternative route for through traffic southbound via A22 Golden
Jubilee Way - A27(T) Dittons Road roundabout North, Polegate
bypass, Cop Hall roundabout, Eastbourne Road - A2270 Eastbourne
Road, Willingdon Road, Crossways roundabout - A2021 Kings Drive,
Rodmill roundabout - A2280 Cross Levels Way, Upperton Farm
roundabout, Cross Levels Way, Broadwater roundabout, Cross Levels
Way - A22 Lottbridge roundabout, Highfield Link, Shinewater
roundabout and northbound via A22 Shinewater roundabout, Highfield
Link, Lottbridge roundabout - A2280 Cross Levels Way, Broadwater
roundabout, Cross Levels Way, Upperton Farm roundabout, Cross
Levels Way - A2021 Rodmill roundabout, Kings Drive - A2270
Crossways roundabout, Willingdon Road, Eastbourne Road - A27(T)
Eastbourne Road, Cop Hall roundabout, Polegate bypass, Dittons Road
roundabout North - A22 Golden Jubilee Way.
The Order commences 26 March 2026 and lasts for a period of 18
months, or until works are completed, whichever is earlier.
However, it is anticipated works will be undertaken from 19:00hrs
to 05:00hrs on the dates detailed below depending upon the weather
conditions.
Between 26 & 28 March 2026
Between 11 & 14 May 2026
Between 27 & 30 July 2026
If you require further information telephone Network Management on
0345 60 80 193.