Additional events outside of the existing
brief were included during and after public consultation following
a request from the Town Deal Board to ensure key stakeholder groups
had been engaged at a more detailed level than at the public
events. This required alterations to the consultancy support
contract including an increase in scope, length and value.
This added benefit to the scheme as we could understand and discuss
issues, concerns and potential mitigations with key groups who had
not attended the public events. The additional post-consultation
events have helped us to achieve our objective of co-designing the
scheme and have been necessary for seeking feedback on potential
changes to the design following the consultation report data.
There is a business need for these new activities to ensure a
comprehensive project consultation.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 13/06/2024
Decision due: 28 May 2024 by Director of Communities, Economy and Transport
Contact: Rupert Clubb, Director of Communities, Economy and Transport Email: rupert.clubb@eastsussex.gov.uk.