Award of contract, following the conclusion of a procurement process, to a consultant to undertake a detailed design for the A22 MRN corridor scheme.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Item Deferred
Divisions affected: Arlington, East Hoathly and Hellingly; Hailsham Market; Hailsham New Town; Pevensey and Stone Cross; Polegate and Watermill; Willingdon and South Downs;
Notice of proposed decision first published: 30/09/2024
Decision due: March 2025 by Director of Communities, Economy and Transport
Lead member: Lead Member for Transport and Environment
Lead director: Director of Communities, Economy and Transport
Department: Communities, Economy and Transport
Contact: Jon Wheeler, Team Manager - Infrastructure Planning & Place 01273 482212 Email: jon.wheeler@eastsussex.gov.uk Tel: 01273 482212.